By
Ranjan Chandran, Partner (Commercial & Construction Department)
Chandni Anantha Krishnan, Associate (Commercial & Construction Department)
Harneshpal Karamjit Singh, Associate (Commercial & Construction Department)
2020 3 MLRA ix
[1] More than seventy countries have declared some form of national level
curfew and/or lockdown ever since the World Health Organization (“WHO”)
declared COVID-19 a pandemic . We are living in unprecedented times as
billions of people Worldwide have their movements restricted.
[2] Locally in Mala ysia, the Go vernment imposed the Movement Control
Order (“MCO”) pursuant to the Prevention and Control of Infectious Diseases
1988 and the Police Act 1967. The MCO was meant to be in effect for 14 days
from 18 March 2020 but has now been extended three times up until the 12
May 2020. There is every possibility of a possible fourth extension or more.
[3] All Malaysians have been advised to comply with the advice to stay put at
home to contain the spread of this dangerous virus which is fast spreading and
causing deaths.
[4] Similar to all layers of the Malaysian population, the building/construction
industry was taken by surprise when the Mala ysian Government announced
the MCO. The Ministry of Works has confr med that the said Industry is
likewise subjected to the MCO.
[5] No doubt certain “Critical Works” construction projects are allowed
to continue works during the MCO , this is however strictly confined to the
continuation of projects , in instances where if it was stopped abruptly, may
cause danger and harm to construction workers, the general public and the
environment.
[6] During the third phase of MCO, the construction industry, specifcally
construction projects and services related to construction works were a few
selected sectors permitted to operate . Be that as it may, from the 19,077
construction companies that had applied to the Ministry of International Trade
and Industry, only 1,856 companies were approved and allowed to operate.1
[7] As a result, most Developers are currently facing major diffculties with
works essentially stopped, with much anxiety and grave concern on how the
construction/building works will be completed with this current pandemic and
MCO constraints.
[8] It is no secret that Developers and construction projects are undoubtedly
adversely affected in this current MCO conditions and which will extend post
COVID-19.
[9] Obtaining supplies and workforce mobility are currently impeded with not
only a national lockdown but the lockdown and curfews in most countries in
the world grappled with this Pandemic. The hardship to the Developers will
be more obvious, especially if the supplies, the workforce and the expertise are
procured from outside Malaysia, where these countries may still be under the
imposition of some form of curfew and/or lockdown.
[10] For the purchasers who have in vested their hard-ear ned money to
purchase properties, their concern will in variably be that the Developer
completes the project on time as covenanted and there is no deferment or delay
in completion occasioned by the COVID-19 pandemic and MCO lockdown
periods.
[11] If there be any delays, purchasers will want to be compensated by virtue
of the Liquidated Ascer tained Damag es (“LAD”) clause in their Sales and
Purchase Agreements (“S&P”).
[12] From the perspective of Developers, there are two possible reliefs that
they may fall back on from their Contract namely:
[13] The two legislations that are paramount in considering the obser vations above are the Housing Development (Control & Licensing) Act 1966 (“HDA") and the Housing Development (Control and Licensing) Regulations 1989 (“HDR”).
[14] The HDA and HDR, which are legislations with the primary intention of
protecting purchasers, have prescribed form HDR S&P, most notably Schedule
G and Schedule H that does not contain a Force Majeure clause. It is trite law
that our Courts will not infer such a clause in its absence.
[15] The doctrine of Frustration which is the usual alternative relief in contract
is further not available for the prescribed form HDR S&P. This will be explained
with reference to the decision of our Court of Appeal in Sentul Raya Sdn Bhd v.
Hariram Jayaram & Ors And Other Appeals (“Sentul Raya”)2 hereinafter.
[16] It will become apparent from case study analysis, that the intention of
Parliament and the cour ts under the HDA and HDR regime is to protect the
interest of purchasers by ensuring that constr uction of projects are completed
as scheduled and De velopers do not misuse the la w to unnecessaril y dela y
completion of projects or abandonment thereof.
[17] The HDR came into force on 1 April 1989 by vir tue of the po wers as
conferred upon the Minister pursuant to s 24 of the HDA.
[18] The rele vant sub-regulation that is to be focused on to see if any relief
is of avail to a De veloper is Sub-regulation 11(3) of the HDR which reads as
follows:
“Regulation 11. Contract of Sale 11(3) Where the Controller is satisfed that o wing to SPECIAL CIRCUMSTANCES OR HARDSHIP OR NECESSITY COMPLIANCE with any of the provisions in the contract of sale is IMPRACTICABLE OR UNNECESSARY, he may, BY A CERTIFICATE IN WRITING, WAIVE OR MODIFY such provisions…”
Sentul Raya
[19] As mentioned earlier , there is then the decision of our Cour t of Appeal
in the case of Sentul Raya which considered the application of Sub-regulation
11(3) of the HDR.
[20] In Sentul Raya, Sentul Raya Sdn Bhd a housing De veloper, governed by
the HDA and HDR, entered into S&P with the purchasers to sell apartments in
a condominium which Sentul Raya Sdn Bhd agreed to construct.
[21] However, Sentul Raya Sdn Bhd w as unable to make deli very of the
apartments and the purchasers commenced action to reco ver LAD for late
delivery of VP of their respective apartments.
[22] Of the many grounds put forward by Sentul Raya Sdn Bhd to resist
the LAD claim, one g round that w as raised w as whether the Doctrine of
Frustration was applicable?
[23] The Cour t of Appeal in the Sentul Raya held that Sub-regulation 11(3)
of the HDR clearl y excluded the operation of the Doctrine of Frustration in
respect of contracts regulated under the HDA regime. In short, the defence of
Frustration was not available to Sentul Raya Sdn Bhd.
[24] The Court of Appeal further dismissed the argument advanced by Sentul
Raya Sdn Bhd that the 1997 Financial Crisis rendered the contracts entered
radically different. The Court held that the 1997 Financial Crisis merely made
it more onerous or perhaps more expensive for Sentul Raya Sdn Bhd to perform
its obligations.
[25] In Sentul Raya, the 1997 Financial Crisis aside from being an impediment
in terms of fnancial constraints to complete the housing development project,
was not a suffcient reason to frustrate the S&P executed.
[26] The decision of Sentul Raya completely favors the purchasers by sending a
clear message to Developers that the cour ts shall not condone any attempt by
Developers to bring an end to the development contracts.
Ang Ming Lee & Ors v. Menteri Kesejahteraan Bandar, Perumahan Dan Kerajaan
Tempatan & Anor And Other Appeals (“Ang Ming Lee”)3
[27] In Ang Ming Lee, the Developer (BHL Construction Sdn Bhd) entered into
the prescribed form Schedule H S&P with the purchasers . In accordance with
the said S&P, the Developer was required to deliver VP of the property to the
purchasers within 36 months of the S&P.
[28] The Developer applied for an extension of time to the Controller pursuant
to sub-regulation 11(3) of the HDR. The reasons for the application was due to
the numerous complaints by nearby residents on the extended working hours;
stop work orders issued by the local authorities; and in vestigations conducted
on the piling contractor. The Controller rejected the Developer’s application.
[29] The De veloper appealed as against the decision of the Controller to the
Minister of UrbanWellbeing, Housing and Local Government pursuant to reg
12 of the HDR. It was purportedly approved and a further 12 months extension
was granted to the Developer.
[30] The purchasers were dissatisfed with the decision of the said Minister as
they were unable to claim for LAD and they commenced a civil suit for judicial
review.
[31] The following questions were posed before the Federal Court:
[32] The Federal Court held as follows:
[33] The decision in Ang Ming Lee is an e xtremely fair decision based on the
peculiar factual circumstances of that case , as the paramount intent of the
HDA and HDR is for the protection of the interest of the purchasers.
[34] The Minister and the Controller ought not to willy-nilly grant extensions
of time for Developers to complete the housing development projects without
obtaining the consent of the purchasers and more so at the expense of depriving
the purchasers of their entitlement of LAD which will be unfair and unjust to
them as it is part of the covenant.
[35] The decision in Ang Ming Lee balanced the commercial interest of a multi-
million housing development company against the life-time loan commitment
of a purchaser for a basic living necessity.
[36] It is no w evident that the HD A and HDR fa vors the purchasers’ rights
and protects them as Force Majeure clauses are not contained in the prescribed
form HDR S&P. The Doctrine of Frustration does not fnd bene volence with
our Courts and sub-regulation 11(3) of the HDR has been declared ultra vires.
[37] As much as we fully support the true purport and intent of the HDA and
HDR to afford the protection to the purchasers that they deserve, the law must
be seen to be fair to consider the plight of the Developers, especially so in this
time of the COVID-19 pandemic and MCO lockdown.
[38] It must be borne in mind that the present scenario of a Developer in the
present COVID-19 pandemic and post COVID-19 is a far cry from the facts of
Sentul Raya then decided.
[39] In the 1997 Financial Crisis , there w as no special circumstances or
hardship like in the present CO VID-19 pandemic and/or the MCO imposed
by the Government.
[40] The special circumstances and hardship in the present CO VID-19
pandemic and MCO will be the complete standstill and permanent closure
of the development project so as to contain the serious risk and spread of this
alarming and dang erous disease that has affected not onl y Malaysia but the
wholeWorld at large.
[41] There are many roadblocks e verywhere to pre vent the mo vement of
people, and workers are advised to stay safe at home. Mobility of construction
workers in this cur rent time is vir tually impossible . There ha ve been many
arrests for those who have breached the MCO.
[42] Procuring supplies for the constr uction project is y et another major
problem, as most suppliers ha ve closed their businesses since the
announcement of the MCO.
[43] In essence, the 1997 Financial Crisis as ad verted to in Sentul Raya is by
no stretch of the imagination any w ay a comparison to special circumstances
and hardship faced by the Developers due to the COVID-19 pandemic and the
MCO.
[44] One may go that far as to say that, the special circumstances and hardship
that the Developers have to endure now, is of a greater complexity and concern
unimaginable with at present three MCO phases imposed completely crippling
the progress of any construction project.
[45] The doors would seem to have been permanently shut for any recourse to
the Developer in Ang Ming Lee by the Cour t declaring sub-regulation 11(3) of
the HDR as ultra vires the HDA. The Appeal to the Minister on any rejected
decision by the Controller under reg 12 of the HDR has presumabl y become
redundant.
[46] It is noted that despite the decision ofAng Ming Lee, the legislature has not
formally repealed the said Sub-regulation 11(3) of the HDR and the reasons
are still left unknown.
[47] The Cour ts will be respectfull y urged to take note of an impor tant fact,
that both the factual matrix of Sentul Ra ya and Ang Ming Lee did not deal
with an unprecedented pandemic situation of COVID-19 or the imposition of
an MCO.
[48] Undoubtedly what is paramount under the HD A regime is protection
of the purchasers’ rights and interest, but ill-affording any recourse to the
Developer is unjust and may well be self-defeating to the purchasers as projects
may be abandoned if the developer is cash strapped.
[49] Perhaps the time has come for the cour ts to impl y terms by the process
of constr uction and inter pretation, incor porating the good faith principle by
judicial activism in contractual relationships.
[50] The ‘Good F aith’ principle is a g eneral principle recognized in most
civil law countries . It is a ter m that describes honest dealing . It is the duty
to act in good faith where contracting par ties are to act with fair ness and/or
reasonableness in performing their covenants.
[51] In § 1-203 of the Unifor m Commercial Code of the United States of
America (“US”) states every contract or duty within the said Act imposes
an obligation of good faith in its perfor mance or enforcement. Similarl y, in
§ 205 of the R estatement (Second) of Contracts of the US states that e very
contract imposes upon each par ty a duty of good faith and fair dealing in its
performance and its enforcement.
[52] This means that e very contract in the US has an implied ter m of good
faith. Contracting par ties are implied to do nothing that ma y impede one
another from enjo ying the fr uits of the contract. Ho wever, e ven in the US
specifcally Califor nia, the breach of good faith will onl y be allowed if there
exists a ‘special relationship’. The elements that need to be satisfed to pro ve
‘special relationship’ is as follows:
[53] Is demanding LAD payment conscionable and fair given the current state
of affairs? Is it conscionable to impose the time for completion in the given
state of affairs? The answer will be an affrmative No.
[54] It is hoped that Mala ysia will become only the four th Commonw ealth
country to recognize this good faith principle . Judicial innovation will be
required to develop this good faith principle to tackle the hardship and special
circumstances that De velopers shall face in completing their contractual
obligations.
[55] The Developer can be assumed to have acted at all times in good faith in
their project development and their works hampered due to an immediate stop
for this COVID-19 pandemic and MCO lockdown period. The Developer had
not acted in any way dishonest, unfair and/or unreasonable in perfor ming its
covenants.
[56] The principle of good faith (if pro ven) m ust be applied to allo w an
enlargement of time/e xtinguishment of LAD computation for a fair and
just period. As if such principle is not implied, it would be unconscionable
to demand LAD and impose completion of the covenants of the S&P in the
current situation.
[57] Furthermore, the Court of Appeal in Aseambankers Malaysia Bhd & Ors v
Shencourt Sdn Bhd & Anor5 stated it would be an unwise decision to summarily
dismiss the existence of a duty of good faith in contracts.
[58] The time is right for our cour ts to apply the good faith principle to fnally
settle the law on the said principle. The current COVID-19 pandemic and the
MCO demands for the recognition of such a principle in Malaysia.
[59] Malaysia urgently needs a COVID-19 Act of Parliament modelled in the
same fashion like that of the Singapore’ s COVID-19 (Temporary Measures)
Act 2020 (“CTM 2020”).
[60] The CTM 2020 has afforded some protection to Developers of projects by
expressly stating that the LAD computations for the six months period of the
CTM 2020 are to be ignored andthere can be no claims by the purchasers. This
is indeed a w elcome relief to Developers in Singapore that m ust be seriously
considered in the proposed Malaysian COVID-19 Act.
[61] In conclusion, the principles of justice and fair ness should be fe xibly
applied together with the good faith principle, which must offer some recourse
and/or relief to the De veloper in this CO VID-19 pandemic and MCO
lockdown period, to grant reasonable extension of time to complete the project
and to waive or extinguish LAD claims throughout this COVID-19 pandemic
and MCO period.
* The Authors are Advocates & Solicitors of the High Court of Malaya
1 K P erimbanayagam and AM Radhi, “19,077 Contractors Applied but Onl y 1,856
Approved to Operate: New Straits Times” (NST Online, 22 April 2020) https://www.
nst.com.my/news/nation/2020/04/586626/19077-contractors-applied-only-1856-
approved-operate accessed 27 April 2020
2 [2008] 1 MLRA 473
3 [2019] 6 MLRA 494
4 Wallis v. Superior Court, 160 Cal. App. 3d 1109 at 1118
5 [2014] 4 MLRA 104