By
Ranjan Chandran, Partner (Commercial & Construction Department)
Chandni Anantha Krishnan, Associate (Commercial & Construction Department)
Harneshpal Karamjit Singh, Associate (Commercial & Construction Department)
[2020] 3 MLRA xxxvii
[1] Claims and payments of Liquidated Ascertained Damages (“LAD”) in a
Housing Development context have become very contentious in recent years.
In the current COVID-19 pandemic and as we come to the conclusion of the
current Conditional Movement Control Order, it is very likely that Developers
are going to face a tough time completing Housing Development projects
within the stipulated contractual period.
[2] Many Developers are likely to be brought to Court for claims on payments
of LAD. What baffles Homebuyers is that even when the computation of LAD
is expressly provided for in the Sales and Purchase Agreement (“SPA”), the law
on LAD requires LAD to be proved. Such position is erroneous. In this Article,
the Authors explore the locus classicus decision of Selva Kumar Murugiah v.
Thiagarajah Retnasamy [1995] 1 MLRA 188 (“Selva”) and the plethora of cases
that followed concerning the issue of proving actual damages which has shaped
the law on proving LAD in Housing Development Contracts.
The Dilemma In Selva
[3] The facts of this case concerned a dispute between two medical
practitioners namely Dr Selvakumar (“the appellant”) and Dr Thiagarajah
(“the respondent”). The respondent sold his medical practice to the appellant
for RM120,000.00 which was payable by several instalments.
[4] The Agreement between them had a forfeiture clause that in the event the
appellant does breach the terms as agreed, then all monies paid to date of such
breach shall be forfeited absolutely in favour of the respondent as LAD and the
Agreement shall be deemed null and void.
[5] The appellant paid a total of RM96,000.00 for the purchase of the medical
practice, which included an earnest money of RM12,000.00 which was paid
upon signing of the Agreement. The balance of RM60,000.00 was to be
paid by 15 monthly instalments. However, six monthly instalments totalling
RM24,000.00 were defaulted.
[6] The respondent terminated the contract and forfeited the entire amount of
RM96,000.00 paid by the appellant as damages and sought a declaration that
he was entitled to the said forfeiture.
[7] The Federal Court had to decide if said forfeiture by the respondent was
valid and enforceable in law.
[8] It is in this context that the Federal Court had the occasion to consider the
application of s 75 Contracts Act 1950 that read:
‘When a contract has broken, if the sum is named in the contract as the
amount to be paid in case of such breach, or if the contract contains any
other stipulation by way of penalty, the party complaining of the breach is
entitled, whether or not actual damage or loss is proved to have been caused
thereby, to receive from the party who has broken the contract reasonable
compensation not exceeding the amount so named or, as the case may be, the
penalty stipulated for’.
[9] The Federal Court decided in favour of the appellant and ordered the
respondent to refund the sum of RM84,000.00. The court, in considering the
application of s 75 Contracts Act 1950, gave a comprehensive picture on its
interpretation by concluding that the qualifying words ‘whether or not actual
damage or loss is proved to have been caused thereby’ are limited or restricted
to those cases where the court would find it difficult to assess damages for the
actual damage or loss.
[10] From a careful reading of the facts of Selva, it will immediately become
apparent that the facts of the said case was simply a partnership dispute and
focused on a claim of damages in conjunction with the right of forfeiture. It
was in this context that the court made the emphatic statement that damages
claimed must be actual loss or damage.
[11] The facts of Selva did not concern a claim for LAD in a housing
development contract between a Purchaser and Developer.
[12] This is where the sentiments as expressed by the Federal Court is of
concern to purchasers in a housing development contract, since the court
held that in any case where there is inherently any actual loss or damage from
the evidence or nature of the claim, and damage for such actual loss is not
too remote and could be assessed by settled rules, then any failure to bring
in further evidence or to prove damages for such actual loss or damage, will
result in the refusal of the court to award such damages, despite the words in
question.
[13] Whilst in Selva, the need for the proof of actual loss and damage or at the
very least a reasonable compensation amount, can be appreciated as there was
absolutely no way of determining the liquidated amount of damages payable,
this position must be contrasted with a housing development contract between
a Purchaser and Developer.
[14] In a standard housing development contract between the Purchaser and
the Developer, there is the specific clause on liquidated damages that spells
out the entitlement of a purchaser to claim LAD for late delivery of vacant
possession.
[15] The LAD clause expressly provides the percentage of claim that a
purchaser is entitled, which usually is a computation of 10% of the purchase
price calculated from day-to-day if the developer fails to hand over the vacant
possession within the stipulated period. As such, the agreement itself spells out
the time period for the developer to deliver Vacant Possession to the purchaser.
[16] There is also the LAD for failure to complete the common properties
within the stipulated period as covenanted in the agreement.
[17] A sample LAD clause is reproduced hereinafter with reference to a case
authority of Sentul Raya Sdn Bhd v. Hariram Jayaram & Ors And Other Appeals
[2008] 1 MLRA 473 (“Sentul Raya”).
[18] With such a simplistic mathematical calculation to compute the LAD
payable by the Developer to the purchaser from the date of the contractual
completion date to the date of actual delivery of Vacant Possession, the issue
of proving actual loss and damages is of no purpose.
[19] This is where the Federal Court when the opportunity does arise, may
wish to re-look and/or revisit the decision of Selva and make a categorical
qualification and exception that for LAD claims in Housing Development
contracts, there is no necessity for the proof of actual proof or damage.
[20] A lower threshold of proof will suffice since the mode of computation of
LAD is expressly covenanted by both parties. All that the Court needs to be
convinced is that the calculation of LAD is correct based on the commencement
of computation and the cut-off date of computation.
Johor Coastal Development Sdn Bhd v. Constrajaya Sdn Bhd [2009] 1 MLRA
654 [C] (“Johor Coastal”)
[21] The facts of this case concerned Johor Coastal Development Sdn Bhd
(“the appellant”) and Constrajaya Sdn Bhd (“the respondent”) that had entered
into two identical SPAs, whereby the respondent agreed to purchase lots 7 and
14 of Johor BahruWaterfront City for RM4,590,000.00 and RM10,830,000.00
respectively.
[22] The respondent was to pay the purchase price by six instalments. The
initial payment of 12% was made followed by the subsequent payment of 50%.
The respondent defaulted in the balance payments.
[23] The appellant terminated the SPAs and forfeited all the monies paid by the
respondent as per the terms of the SPAs.
[24] The issue in the Federal Court was whether the appellant was entitled to
forfeit all the monies paid by the respondent.
[25] The Federal Court decided that the appellant cannot retain the monies
without proof by evidence of the loss or damage suffered as a result of breach
of the SPAs.
[26] The Federal Court in the Johor Coastal held Selva to be good law, that
actual damages or reasonable compensation must be proved in accordance
with the principles set out in English case of Hadley v. Baxendale [1854]
EWHC J70.
[27] The Federal Court held that 10% or 12% which is to be forfeited by the
Appellant is not to be challenged by the respondent as not being fair and
reasonable compensation. As for the balance, it was held that it was not open
for the appellant to keep all the monies and the balance had to be returned to
the respondent.
[28] The facts of the Johor Coastal like Selva was glaringly distinct, as this case
did not concern a claim for LAD in a Housing Development contract between
a Purchaser and Developer.
[29] The same reasoning as explained earlier for Selva will apply, as there is
no necessity to prove actual loss or damage where the terms of the Housing
Development contract between a purchaser and a Developer has a LAD clause
with the percentage and computation as agreed spelt out with clarity.
[30] Both the decisions of Johor Coastal and Selva were focused on the issue
of forfeiture of deposits and both did not concern a LAD claim in a Housing
Development contract.
Cubic Electronics Sdn Bhd v. Mars Telecommunications Sdn Bhd [2019] 2 MLRA
83 (“Cubic Electronics”)
[31] In Cubic Electronics, Mars Telecommunication Sdn Bhd (“the
respondent”) had agreed to purchase a piece of land for RM90,000,000.00
from Cubic Electronics (“the appellant”) by accepting the appellant’s
information memorandum dated 15 September 2011. The respondent made
the first earnest deposit on 3 October 2011 amounting RM1,000,000.00. The
acceptance was subject to a term in the information memorandum which
stated that the SPA should be executed within 30 days of 7 October 2011,
failing which, the earnest deposit would be forfeited as agreed liquidated
damages.
[32] Three further extensions were granted and three further deposits were
made amounting to RM2,040,000.00 including RM40,000.00 interest. The
respondent was cautioned that the deposits made would be forfeited as agreed
liquidated damages if the SPA was not executed as per the granted extensions.
It was when the respondent requested for a fourth extension, the appellant
refused the request and terminate the sale. The appellant informed that all
deposit payments made were forfeited accordingly.
[33] The Federal Court was concerned with the issue of whether where terms
and conditions of the SPA had been agreed to and a date was fixed for the
execution of the SPA, can any additional deposit paid for the extension of time
for completion be equally subject to forfeiture.
[34] The Federal Court noted that the focus of the issue is on the treatment of
deposits vis-à-vis Section 75 of the Contracts Act 1950.
[35] Relying heavily on the literature of English and Indian case law, the
Federal Court held that it was time for Malaysia to adopt the principles of
law pertaining to a damages clause, to be equally applicable to forfeiture of
deposits.
[36] Section 75 of the Contracts Act 1950 operates as a vital curtailment of
absolute freedom of contract, designed to check against potential abuse by a
party at another’s expense. As such, parties are not at liberty to contract out of
s 75 of the Contracts Act 1950.
[37] As long as a payment has the dual characteristics of earnest money
and part payment, it will be deemed as a deposit and subject to s 75 of the
Contracts Act 1950. In determining what is “reasonable compensation”
under s 75 of the Contracts Act 1950, the Courts must apply the principles
of “legitimate interest” and “proportionality”. Only if the amount of
compensation is extravagant and unconscionable, it will be considered
unreasonable compensation. Otherwise, the damages provided for in the
contract should mirror the loss/damage likely suffered by the innocent party.
[38] Section 75 of the Contracts Act 1950 allows reasonable compensation
regardless whether actual loss or damage is proven. Actual loss should not be
the sole consideration of reasonable compensation but evidence of that may
be a useful starting point.
[39] The burden of proof is divided to primary burden of proof and secondary
burden of proof.
[40] The primary burden of proof is where the Innocent party seeking to
enforce damages clause under s 75 of the Contracts Act 1950 needs to prove
breach of contract and the contract provides for a clause specifying a sum
to be paid upon breach. At this stage, if the innocent party is successful in
establishing the primary burden of proof, the innocent party becomes entitled
for a sum not exceeding the amount stipulated in the contract irrespective of
whether actual damage or loss is proven. The secondary burden of proof then
comes into play where the defaulting party is entitled to prove that the sum
stated in the damages clause is unreasonable including if there is a dispute as
to what constitutes reasonable compensation.
[41] The Federal Court held that parties were well aware of the fact that
earnest deposit payments would be forfeited as “agreed liquidated damages”.
The deposits were subject to the same test of “legitimate interest” and
proportionality” of the damages clause under s 75 of the Contracts Act 1950.
[42] Among others, the deprivation of chances for the appellant to enter into
negotiations with third parties, goal of securing the execution of the SPA and
avoiding delay in its completion were all “legitimate interest”. The total deposit
amounted to 3.33% of the purchase price, which was deemed proportionate
under the principle of “proportionality”. In turn, the respondent could not
prove that such amount was unreasonable or exorbitant. The deposits were
reasonable compensation under s 75 of the Contracts Act 1950.
[43] It must be borne in mind that similar to both the decisions of Johor Coastal
and Selva, Cubic Electronics focused on the issue of forfeiture of deposits and
did not concern a claim for LAD in the context of a Housing Development
contract.
SENTUL RAYA
[44] The Authors will rely on this decision of our Court of Appeal in Sentul
Raya to fortify the contention, that the time is ripe for our Federal Court to
revisit the decision of Selva.
[45] This is supported by the fact that Sentul Raya was a case concerning a
Housing Development contract which is the main borne of contention in
advocating a change in the law of proof of damages.
[46] The brief facts are that Sentul Raya Sdn Bhd, a housing developer, whose
activities are controlled by the Housing Development (Control and Licensing)
Act 1966 and Housing Development (Control and Licensing) Regulations
1989 (“HDR”) thereunder entered into agreements with members of the
public to sell them apartments in a condominium which Sentul Raya Sdn Bhd
agreed to construct.
[47] However, Sentul Raya Sdn Bhd was unable to make delivery of the
apartments and Hariram Jayaram and others commenced action to recover
damages for late delivery of vacant possession of their respective apartments.
[48] The relevant clauses in the Statutory Contract prescribed by Sub-
Regulation 11(1) of the HDR on the entitlement of LAD were cls 22 and 24.
[49] Clause 22(2) of the SPA on the LAD for the parcel/unit reads:
‘If the vendor fails to hand over vacant possession of the said parcel to which
water and electricity supply are ready for connection to the said parcel, in
time, the vendor shall pay immediately to the purchaser liquidated damages
calculated from day to day at the rate of ten percent (10%) per annum of the
purchase price’.
[50] Clause 24 of the SPA on the LAD for the common properties reads:
‘The common facilities serving the said housing development shall be
completed by the vendor within thirty-six (36) calendar months from the date
of this agreement.
‘If the vendor fails to complete the common facilities in time the vendor shall
pay immediately to the purchaser liquidated damages to be calculated from
day to day at the rate of ten percent (10%) per annum of the last twenty per
cent (20%) of the purchase price.’
[51] The salient part of the judgment of Sentul Raya that is of relevance here
is the purchasers were not under a duty to prove the damages that they had
suffered because the LAD clause was a statutory contract that provided that
damages were liquidated and calculated in accordance with the formula
prescribed by the clause and that no further onus lay upon the purchasers.
[52] The Court went further to say that once the date for delivery of vacant
possession had passed, the developer’s liability to pay liquidated damages
calculated in accordance with the formula provided in the said LAD clause
became immediate.
[53] This is in the respectful views of the Authors should be the correct
proposition of the law on the proof of damages for Housing Development
agreements as the need to proof actual loss should not arise where there is a
prescribed formula for computation in the SPA.
[54] The losses are easily quantifiable and it is easy to compute the liquidated
amount payable by the developer to the purchaser.
[55] The need to proof actual loss when there is already a computation and
formula prescribed imposes an unnecessary onerous task on the entitlement
of the purchasers on their rightful entitlement to LAD on account of the delay
in completion of their parcel/units and delay in completion of the common
properties.
[56] The begging question of the purchasers of a Housing Development will
then be as to why is there a need to proof actual loss of damages suffered when
parties have covenanted on their entitlement to LAD.
[57] The decision in Sentul Raya is a very practical decision which should be
the position in law for housing development contracts.
[58] In fairness, the facts of the cases of Selva, Johor Coastal and Cubic
Electronics were a far cry from the facts of the Sentul Raya, as all these three
cases were not cases concerning Housing Development. The factual matrix in
the said cases did not deal with an agreement with an express clause on LAD.
[59] This explains the reason why the decision of Sentul Raya decision was not
referred to in any one of the said decisions by the Federal Court.
[60] The Authors having expressed their views, are of the opinion that the
time is right to revisit the decision of Selva and to distinguish or depart from
the said decision to clarify the position on the law proving LAD in Housing
Development contracts.
[61] The Authors are mindful of the fact, that the Honourable Federal Court
Judges, when the occasion does arise, will adopt the findings of the Court of
Appeal in Sentul Raya in its totality.
[62] A purchaser in a Housing Development transaction ought not to be
troubled to prove damages in a LAD claim especially since the computation of
such claim is covenanted in the Housing Development SPA.
[63] The correct position for the Law on proving LAD in a Housing
Development context should be the total removal of the need to proof actual
loss and damages. This position would be in line with the covenants of the
Housing Development SPA whereby the formula for computing LAD is
already covenanted in the said SPA.
[64] As long as the Developer has defaulted by not delivering vacant
possession within the stipulated period, the Developer should be
immediately liable to pay LAD in accordance with the covenants of the
Housing Development SPA. Such position is also consistent with commercial
and contract law where the freedom of contract must prevail and covenants of
such contracts must be respected and given effect.